Sequences And Series PYQJEE Main 2024 (Online) 6th April Evening Shift
A software company sets up m number of computer systems to finish an assignment in 17 days. If 4 computer systems crashed on the start of the second day, 4 more computer systems crashed on the start of the third day and so on, then it took 8 more days to finish the assignment. The value of
Solution
Correct option: C
Write The Original Work
With
Model The Crashes
The assignment actually takes
This is an AP with first term
Sum The Actual Work
Total work done in 25 days is
Equate Both Work Values
The total work is unchanged, so
Solve For \(m\)
From
Therefore, the correct option is C.